RAW2021 – Modeling Environmental Constraints in Capital Projects RISK-ACADEMY Blog

0
348

Наши популярные онлайн курсы

sample85
+ Подробнее

Риск-ориентированное управление. Самостоятельно

Курс направлен на развитие навыков риск-ориентированного мышления, которое позволяет выявлять, приоритезировать и моделировать влияние рисков на ключевые цели или решения организации.

25000 руб
sample85
+ Подробнее

Риск-ориентированное управление. С преподавателем.

Крупнейшая в России программа онлайн-подготовки к двум сертификациям: национальной и международной G31000

45000 руб
sample85
+ Подробнее

Количественная оценка рисков

Единственный в России и СНГ онлайн-курс по количественной оценке рисков и принятию решений.

33000 руб

Capital projects all over the world – both onshore and offshore – encounter strict environment protection regulations that become increasingly demanding. For example, construction could be forbidden in particular annual seasons to allow breeding of various mammal, bird, marine or insect species. These impose strict and mandatory environmental constraints on project schedules. Although, just incorporation of the environmental constraints into project schedules cannot adequately forecast project completion dates due to various risk factors that severely exacerbate the constraints.

When the environmental constraints are properly incorporated into project schedules:

• regular project risks including environmental/ permitting risks should be imposed on (“mapped to”) the project schedules,

• project-system-delivery issues (“systemic risks”) should properly modify regular project risks including environmental/ permitting risks, and

• relevant interactions among project risks including convolution of environmental/ permitting risks with the rest of project risks (“risk interaction mapping”) should be counted for.

The above-listed risk factors give rise to non-linear Monte Carlo schedule risk models. They yield highly skewed and often discontinuous project completion date’s distributions. Such distributions reflecting on the environmental constraints mixed with the above-listed risk factors are capable to predict actual project outcomes rather precisely. A simple non-linear Monte Carlo model built using Oracle Primavera Risk Analysis (“PertMaster”) demonstrates concepts put forward in this report.

https://2021.riskawarenessweek.com/talks/modeling-environmental-constraints-in-capital-projects/

Check out other decision making books

RISK-ACADEMY offers online courses

sample85

+ Buy now

Informed Risk Taking

Learn 15 practical steps on integrating risk management into decision making, business processes, organizational culture and other activities!


19,999,99



sample85

+ Buy now

ISO31000 Integrating Risk Management

Alex Sidorenko, known for his risk management blog http://www.riskacademy.blog, has created a 25-step program to integrate risk management into decision making, core business processes and the overall culture of the organization.


199,999,99



sample85

+ Buy now

Управление рисками

В этом коротком и очень увлекательном курсе, Алексей Сидоренко расскажет о причинах внедрения риск менеджмента, об особенностях принятия управленческих решений в ситуации неопределенности и изменениях в новом стандарте ИСО 31000:2018.


19,999,99